V2019pre/Release schedule

From Apertis
Jump to: navigation, search

The v2019pre release cycle started in April 2019.

Milestone Date
Start of release cycle 2019-04-01
2019-04-15
Soft feature freeze: end of feature proposal and review period 2019-05-21
Soft code freeze/hard feature freeze: end of feature development for this release, only bugfixes allowed 2019-06-04
Release candidate 1 (RC1)/hard code freeze: no new code changes may be made after this date 2019-06-11 EOD
RC testing 2019-06-12..25
v2019pre release 2019-06-26

If the release candidate 1 does not successfully pass all required tests, then the issues will be fixed and a new release candidate will be re-tested. This would delay the release, which would be reflected on this page.