The 19.03 release cycle starts in January 2019.
Milestone | Date |
---|---|
Start of release cycle | 2019-01-01 |
Soft feature freeze: end of feature proposal and review period | 2019-02-19 |
Soft code freeze/hard feature freeze: end of feature development for this release, only bugfixes allowed | 2019-02-26 |
Release candidate 1 (RC1)/hard code freeze: no new code changes may be made after this date | 2019-03-12 EOD |
RC testing | 2019-03-13/2019-03-17 |
19.03 release | 2019-03-18 |
If the release candidate 1 does not successfully pass all required tests, then the issues will be fixed and a new release candidate will be re-tested. This would delay the release, which would be reflected on this page.